ACQUISITION OF PROPERTY
Contents:
Scope
Key Points
Background
Statement of Need
Project Sponsor
Option Appraisal
Procurement Options
Non-Quantifiable Benefits
Preferred Option
Negotiations
Acquisition Price
Building and Specialist Surveys
Closing Date
Auctions
Fitting Out
Property Database / Fixed Assets Registers
Post Appraisal Evaluation
Annex:
Property Search Instruction
Scope
1. This section gives guidance on the procedures and
safeguards to be adopted in any proposal to acquire
property i.e. land and buildings and other rights in
property. The guidance is aimed primarily at the
constituent parts of the Scottish Administration (ie
Scottish Executive Departments, Executive Agencies and
associated Departments). However, other organisations
subject to the requirements of the Scottish Public Finance
Manual (SPFM), including sponsored bodies, should ensure
compliance with any relevant provisions and arrange for
procedures consistent with the guidance to be put in
place.
Key Points
2. When a requirement for additional property for
accommodation is being considered business areas within the
Scottish Administration must seek advice from Property
Advice Division.
3. In some cases the acquisition of property will be
part of a major investment procurement to which relevant
guidance in the SPFM applies.
4. It is essential to check if there is suitable surplus
property available within the Scottish Administration or
the wider public sector and, where appropriate and
possible, to acquire property using the Guidelines for the
Transfer of Property within the Scottish Public Sector as
set out in the section of the SPFM on
Disposal
of Tangible Fixed Assets.
5. A decision must not be taken on a particular solution
before a range of options has been fully considered and
appraised. The costs of the options, the results of the
sensitivity testing and the ranking of options in terms of
their outputs and policy considerations should be
considered together to determine which option gives the
best value for money.
6. Possible methods of procurement include purchase,
lease or the provision of serviced accommodation through a
PFI/PPP contract.
7. A proposed acquisition with a cost in excess of the
independent current valuation should be cleared in advance
by the relevant Finance Team.
8. A full building survey is essential before purchasing
or leasing an existing building. It should be sought at the
earliest possible stage.
Background
9. Property transactions by their very nature are
generally expensive and there is scope for substantial
financial loss if they are not handled properly. The
decision to acquire property should be part of an overall
strategic plan for the organisation's needs. Acquiring
property is not necessarily the way to solve operational
problems. Property commitments whether purchases or leases
can be very expensive to reverse.
10. The guidance in this section essentially covers the
acquisition of property for accommodation but is equally
applicable to the acquisition of land and buildings for
other purposes. When a requirement for additional property
for accommodation is being considered business areas within
the Scottish Administration must seek advice from Property
Advice Division. (Other bodies subject to the requirements
of the SPFM may seek advice from Property Advice Division
on a voluntary basis or, in the case of relevant sponsored
bodies, where required to do so under the terms of their
Management Statement / Financial Memorandum.) However,
detailed reference of each case to Property Advice Division
is not necessary for the acquisition of land and buildings
for other purposes provided that appropriate professional
advice is obtained from other sources.
Statement of Need
11. The Scottish Ministers' policy is that property
holdings should be kept to a minimum. The case for
acquiring property for accommodation must be set out as
below to ensure that property is acquired only after the
Statement of Need criteria have been fulfilled. The
Statement of Need criteria is designed to enable a wide
range of alternative options to be considered including
different locations, types of properties and tenures. They
are as follows:
- the number, grade and function of staff to be
accommodated and any further specialised space such as
conference rooms, record storage, cafeteria, etc.
Property Advice Division can give guidance on
appropriate space provision and specialist space
planning consultants.
- the underlying objective must be stated, e.g. a
local office needing to be situated near clients and
close to public transport. Objectives should be in
terms of outputs in order that the range of options is
not constrained. This is especially important in
PFI/PPP financed acquisitions.
- the intended date of occupation must be set out
together with the anticipated period of
occupation.
- any potential breaks or variations in the
requirement that can be anticipated over the life of
the scheme.
12. The Statement of Need gives clear direction to the
search and forms the foundation for the "Instruction" to
external property advisers, when appointed, to identify
suitable properties. More detailed guidance on the
Instruction is set out in the
Annex.
Property Advice Division will assist in drawing up the
Statement of Need, the Instruction and in the appointment
of property advisers.
13. It is essential to check if there is suitable
surplus property available within the Scottish
Administration or the wider public sector and, where
appropriate and possible, to acquire property using the
Guidelines for the Transfer of Property within the Scottish
Public Sector as set out in the section of the SPFM on
Disposal
of Tangible Fixed Assets. (Property acquired using the
guidelines can be acquired without the need for external
property advisers and without incurring unnecessary costs.)
Property Advice Division will advise. There is a strong
presumption in favour of using existing property rather
than acquiring new property. In addition the Scottish
Executive has a relocation policy which requires options
outwith Edinburgh to be considered when property is being
obtained for existing bodies, and has a presumption against
an Edinburgh location.
14. The external property adviser will undertake a
search of the property market and provide a report on all
the alternatives that meet the criteria in the Instruction,
and help the business area and its internal advisers draw
up a short-list.
Project Sponsor
15. In some cases the acquisition of property will be
part of a masjor investment procurement to which relevant
guidance in the SPFM applies. In such instances property
acquisition will be part of the functions of the Project
Manager and the Project Sponsor for the whole project, so a
separate Project Sponsor will not be needed. If the
property acquisition is not part of a larger project the
business area should appoint a Project Sponsor to obtain an
Option Appraisal to plan, co-ordinate and ensure that best
practice is followed. Where other pressures require an
abbreviated procedure and this presents a serious risk to
best practice, the Project Sponsor has a duty to ensure
that the implications are drawn to the attention of the
Accountable Officer so that decisions can be taken on the
way forward. While the Statement of Need is being
developed, the Project Sponsor must seek advice from
Property Advice Division.
16. Further guidance on the role of Project Sponsor is
given in the section in the SPFM on
Major
Investment and advice on the appointment of Project
Managers should be obtained from Construction Advice and
Policy Division.
Option Appraisal
17. An Option Appraisal consistent with the Green Book
must be undertaken in consultation as appropriate with
Analytical Services Division and/or Property Advice
Division to examine the full costs and benefits of
different potential solutions. This will include fixed and
variable costs taken over the life of the project. The
costs to be appraised - these exclude capital charges and
depreciation - will include the following:
- for new build, the construction costs, including
cost of land, consultant fees, fitting out, etc;
- for existing property, the purchase price and
expenditure in adapting the property to meet the
specific needs of the customer;
- rent, service charge, rates, annual repair costs,
insurance if appropriate;
- transaction costs, e.g. professional fees,
premiums, etc;
- repairs, immediate and cyclical, and
decoration;
- dilapidations;
- running costs, services, cleaning, security costs
etc;
- staff costs, travel relocation expenses, removal
costs;
- any unusual or onerous lease conditions;
- any penalties for break options in the lease;
- quantifiable benefits e.g. part of a larger than
necessary building leased out to a third party at a
commercial rate; and
- residual value of the property at the end of the
appraisal period.
18. A decision must not be taken on a particular
solution before a range of options has been fully
considered and appraised - including an analysis of the
risks involved. The Option Appraisal will consider the
availability of existing property, the surrender of
existing property (if appropriate) and other specific
points which may give rise to costs during the appraisal
period.
19. All costs should be as at the date of the appraisal,
which is usually the present date. The costs must be on a
comparable basis throughout the appraisal period which must
be defined. No adjustment should be made for future
inflation although future significant relative price
changes should be included in the calculation. The advisory
team will give advice on costs, timing and discount rates.
The cash flow generated will then be converted into NPV or
NPC terms using the appropriate discount rate - currently
3.5% in real terms on non-commercial projects and 5.5% in
real terms on commercial ones.
20. When the number of options has been reduced
alternative outcomes can be studied by sensitivity testing.
The appraiser can take the preferred and next best options
and see how they respond to changes such as unexpected
rises in costs, the exercising of lease break clauses, or
premature termination, etc.
Procurement Options
21. The options for the procurement of the new
accommodation will form a separate section of the appraisal
document. Possible methods of procurement include purchase,
lease or the provision of serviced accommodation through a
PFI/PPP
contract. PFI/PPP is a form of public private partnership
under which a private operator designs, builds, finances,
owns and operates a building and the public body which
occupies it makes payments which vary according to the
quality of services provided. This arrangement gives the
private sector the scope and incentive to secure
efficiencies in design construction and operation. If
PFI/PPP is being used, the negotiation process will be
quite different from a conventional procurement and will be
conducted under EC procurement procedures on the basis of
an output specification. Advice on the suitability of
projects for PFI/PPP, and on PFI/PPP procurement
methodology is available from the Financial Partnership
Unit within Scottish Executive Finance.
22. For some requirements acquisition by lease should be
considered. Although this avoids the need for capital up
front, a lease is a rigid legal commitment with long-term
cost implications and it should only be undertaken after
receiving professional advice. Acquisition by way of site
purchase and new build is a complicated process that
usually demands time and considerable input from a variety
of professional disciplines. Advice on selecting and
purchasing a site can be obtained from Property Advice
Division and advice on building procurement is available
from Construction Advice and Policy Division.
Non-Quantifiable Benefits
23. In some circumstances, the options will differ
significantly in terms of their non-quantifiable benefits,
such as accessibility, ambience and general environmental
features. These can be assessed using weighting and scoring
methodology. Under this methodology, the different options
can be given a score for each of the factors, such as
accessibility. This will generally be an expert judgement.
Then each of the factors can be given a weight,
representing their relative importance, by the advisory
team. The sum of weighted scores can then be used to rank
the options by their level of output. (This is also a
useful methodology for deriving a short list from the
initial list of options.) Assistance can be provided by
Analytical Services Division.
Preferred Option
24. The costs of the options, the results of the
sensitivity testing and the ranking of options in terms of
their outputs and policy considerations should then be
considered together to determine which option gives the
best value for money. This will not always be the cheapest
option, as other options may offer a much better balance of
benefits to cost, or be significantly less risky. The
budgetary consequences and affordability of the preferred
option must also be considered and it is therefore
essential that a separate financial appraisal is undertaken
and that the relevant Finance Team is involved in the
evaluation process. Once a provisional decision on
appropriate properties or locations has been taken, and the
necessary approvals have been obtained, then negotiations
for particular properties can be opened. As negotiations
proceed, and the final terms of the purchase or sale
emerge, it is necessary to revise the appraisal to ensure
that the provisional decision on the best options remains
valid. This is because appraisal is an iterative process.
As the process brings better information to light the
appraisal should be updated and revised to ensure that the
original assumptions remain valid. The relevant Finance
Team should be informed immediately of any change in
projected costs.
Negotiations
25. The external property advisers' report will suggest
alternatives which the business area will wish to view. It
is advisable for the numbers viewing properties to be small
and to be accompanied by a surveyor from Property Advice
Division. Business areas must refrain from making any
comment on the property to the sellers or their agents as
this may prejudice negotiations and the terms obtained.
26. During negotiations for the preferred option a
fallback option should be pursued where possible to
preserve bargaining power and in case the preferred option
collapses. Options are often dependent upon variables such
as planning consent which may not be forthcoming.
27. As more detailed information is obtained during
negotiations, the appraisal should be continually updated
and refined and provisional decisions re-examined to ensure
that they remain valid.
28. If there will be a delay of 6 months or more between
the initial decision and the conclusion of missives, then
the Project Sponsor should seek advice on whether the
figures should be adjusted, or if a further valuation or
survey is required. This is important if the valuation is
subject to special conditions or if the surveys undertaken
or local knowledge suggests delay which will cause further
expense.
29. When provisional negotiations are concluded the
final package should be put to the Project Sponsor /
business area for approval. A current valuation should be
part of the package. The Heads of Terms of Agreement to
Lease or Purchase must be clearly stated. The Project
Sponsor / business area should consider whether any special
conditions are to be included in the purchase offer and
where none are required positive mention of this should be
included in the instructions to Solicitors. Solicitors will
formally conclude the transaction.
30. Any correspondence on the Heads of Terms between the
business area and the seller/landlord should observe the
Requirements of Writings (Scotland) Act 1995 to ensure that
such correspondence is not legally binding. Accordingly all
correspondence should contain the paragraph:
"For the avoidance of doubt this letter is not intended
to have contractual effect nor to impose or create any
legal binding obligation or liability."
Acquisition Price
31. The price paid on the acquisition by a public body
will be open to scrutiny and it is therefore vital that an
independent valuation is correctly instructed. Acquisition
in excess of the independent current valuation should be
supported by the Option Appraisal showing that the option
represents the best value for money. A proposed acquisition
with a cost in excess of the independent current valuation
should be cleared in advance by the relevant Finance
Team.
32. In PFI/PPP value for money is determined by
comparing the Net Present Value of the whole life costs of
a conventionally procured public sector comparator,
adjusted to reflect all the risks which are to be
transferred to the private sector, with the Net Present
Value of the PFI/PPP payments.
Building and Specialist Surveys
33. A full building survey is essential before
purchasing or leasing an existing building. It should be
sought at the earliest possible stage. Advice on obtaining
a survey must be sought from Property Advice Division.
Where existing properties are to be altered, refurbished,
converted or otherwise developed, building surveys should
always be commissioned prior to any commitment to acquire.
Problems identified may require further investigation.
34. With listed buildings or scheduled monuments it is
particularly important to get specialist advice on what can
be done with the building, what adaptations, if any, will
be allowed, and to assess the future running and
maintenance costs.
35. With new-build options, site investigations will
check that the ground can bear the proposed development,
and ensure that there is no environmental contamination of
the site which may limit the use and value of the site.
Such investigations may also alert business areas to the
presence of archaeological remains which may delay, or
preclude development.
36. With a new building there will normally be a defects
liability period for the occupier to have defects remedied
by the contractor. It is also important to secure
collateral warranties from the building contractor, the
architect and others associated with the building project
and for the missives or the lease to specify the steps to
be taken in the event of latent defects appearing.
37. Where an existing property is taken on lease a
Schedule of Condition must be prepared by a Building
Surveyor and agreed by the landlord and tenant prior to
occupation. This will record the condition and state of
repair and decoration and assist the assessment of any
dilapidations claim by the landlord at the end of the
tenancy. The Schedule of Condition will normally be annexed
as a Schedule to the lease itself so that it forms part of
the signed lease between the parties. The tenant will not
normally have to do any work which would render the
property in any better condition than that disclosed in the
Schedule.
38. The information generated by these surveys and
reports should be fed back into the appraisal to ensure any
hidden costs they reveal are properly taken into
account.
Closing Date
39. In the event of a property being subject to a short
closing date, advice must be obtained from Property Advice
Division on the steps that require to be taken in order to
ensure that value for money considerations still apply.
Auctions
40. Auctions are not common in Scotland. Nevertheless
properties may be acquired in this way and an authorised
agent can bid up to a pre-arranged limit. Auctioneers will
take instructions to do this on behalf of potential
purchasers. One difficulty is that auctioneers usually
require a deposit from the successful bidder at the auction
so a member of staff with authority to sign for large sums
of money will need to be present. As any bid accepted is
binding, the title, surveys and all other investigations
must have been completed before the auction and sufficient
time must be allowed for this to be done. Property Advice
Division and Solicitors must therefore be involved prior to
the auction to carry out the relevant investigations. The
auctioneer may allow a joint deposit receipt system to be
used in instances of difficulty. Property Advice Division
and Solicitors should be asked if they will send a
representative to the auction to advise the business
area.
Fitting Out
41. Fitting out a new building or converting and fitting
out an existing building is fairly specialised work.
Property Advice Division can advise on appropriate
surveyors or property consultants to supervise this work.
Specialist space planners can assist with the design of
layouts to fulfil client's needs and also go on to manage
the fitting out process. The additional time and cost of
fitting out must be taken into account at the appraisal
stage.
Property Database / Fixed Assets
Registers
42. Business areas should inform Property Advice
Division of all acquisitions of property whether for
accommodation or for other purposes to enable the Scottish
Executive Property Database to be updated. The Financial
Reporting Unit within Scottish Executive Finance and, where
appropriate, relevant Finance Teams, should also be
informed so that fixed assets registers can be updated.
Post Appraisal Evaluation
43. A post appraisal evaluation should be carried out
within six months of acquisition being completed to assess
whether or not the appraisal was done as well as possible
and check that the property meets the current need. If the
project involved a major construction contract, a formal
Post Project Evaluation will be required in accordance with
guidance in the
Major
Investment section of the SPFM.
Back to top
Page Published/ Updated on: 27th March 2004